PHILIPS CONSUMER LIFESTYLE
Drop shipment project, including Warehouse- and Order Management System implementation.
Assignment
Connect different sales channels from multiple warehouses, including the implementation of WMS (warehouse management system) in Ingram Micro Milan warehouse.
Challenge
Complexity of different systems to be connected and for the new warehouse set-up there were few resources.
Approach
Created overview on tasks and activities in a Gantt chart and listing issues to be resolved. Hands-on mentality to organise warehouse implementation with remote assistance.
Result
GoLives without major incidents.
“Jolijn is super professional, if you need a project done on time, she is the right person to work with. Well prepared, always available, proactive and positive. She has a strong background on IT and able to play as problem solver, to be honest I cannot say anything bad about her apart from we haven’t had a beer together as I had to drive each time she came to Italy 🙂 I reccomend her and really happy to work again together in the future. While working we faced hard times, she has a sense of humor and a pragmatic way to solve problems which is amazing working with her.”
Mirko Redeker
Supply chain, procurement, operations
TELE2
B2C/B2B logistic consolidation project.
Assignment
Move B2C logistics flow for Tele2 to Ingram Micro Tilburg warehouse with respect to existing system integrations.
Challenge
No handover from previous project manager and unclear agreements on timelines and scope
Approach
Created overview on remaining tasks and activities in a Gantt chart and listing issues to be resolved. Created broad test plans for thorough testing to have trustful GoLive.
Result
GoLive without major incidents, respected the final joint set deadline.
“I’ve had the pleasure to work with Jolijn on several projects. She is both a really nice person to work with and a very dedicated project manager who can draft a project plan, listing all relevant activities, in a blink. During the execution of the project, Jolijn is fully in control of timelines and ensures the project gets delivered on time (or sooner).”
Reinder van der Werf
Director Business Development Ingram Micro Commerce EMEA
MAANDAG®
Kentico Content Management System (CMS) & Salesforce implementation, website & web shop redesign, multiple countries.
Assignment
Implementation of webshops redesign with new CMS (Kentico)
Challenge
System complexity and tight deadlines
Approach
Listed user stories for requirements, created overview on tasks and activities in a Gantt chart and listing issues to be resolved.
Result
GoLive of all country webshops with respect to deadlines.
FrieslandCampina
(Lattiz & Vifit Sport) – B2C/B2B web shop launches (CS, Warehouse & Logistics).
Assignment
System integrations for B2C and B2B webshop launches.
Challenge
New platform to be used.
Approach
Adapted the Business Requirements Document on the new platform, created Gantt chart and action logs to follow up on tasks and activities including third party (webshop creation).
Result
Handed over the project to account manager for GoLive and hypercare.